Skip to main content

"Can you have it ready by next week?" is one of the top three questions I hear during scoping calls. The honest answer is almost always "no, but I can ship something useful sooner than you think if we narrow the scope." Here's what realistic delivery actually looks like.

Quick reference: website timelines

Project typeRealistic timelineRush timeline
Single landing page1–2 weeks3–5 days
5–8 page business site2–4 weeks10–14 days
Site with CMS / blog3–6 weeks2–3 weeks
E-commerce store4–10 weeks3–5 weeks
Custom web app (MVP)6–14 weeks4–8 weeks
SaaS product (full v1)3–9 months2–5 months

What "ready" actually means

Most clients underestimate the gap between "design is done" and "the site is live." A real launch checklist looks like:

Each item adds days. Skipping them adds weeks of post-launch firefighting.

What actually slows projects down

Client-side delays (the #1 cause)

Most projects don't slow because of code. They slow because the client takes 6 days to send back feedback on a design proposal. A 4-week project becomes a 10-week project with three rounds of "I'll review this over the weekend." If you want fast delivery, commit to 24–48 hour feedback turnaround.

Scope creep

"Can we also add..." kills more timelines than any technical issue. Healthy project management means writing scope down, treating new requests as change orders, and being explicit about timeline impact.

Third-party integrations

"Just hook this up to our CRM" can be 2 hours or 2 weeks depending on whether the CRM has a real API, sandbox, and clear docs. Always pad estimates for integrations.

Content debt

If real copy and images aren't ready, design has to start from placeholders. Then you redesign when real content arrives because the placeholder lengths were wrong. Have content ready first.

The phases

For any non-trivial project I run four phases:

  1. Discovery (week 1) — scoping, technical decisions, design direction.
  2. Design (weeks 2–3) — wireframes then high-fidelity mockups for at least the home and one inner page.
  3. Build (weeks 3–N) — staged on a private URL the client can review weekly. New routes show up incrementally.
  4. Launch & support (final week + 30 days) — production deploy, content migration, training, then a month of post-launch fixes baked in.

For tiny landing pages I collapse design and build into one phase. For SaaS work I add a "validation" phase before discovery where we sketch the smallest possible v1 that proves the idea.

How to actually get a fast delivery

How long would your project take?

Send me what you're building at m2hgamerz.prince@gmail.com with a rough scope. I'll come back with a realistic timeline within 24 hours. Free, no obligation.